Research Article - (2022) Volume 12, Issue 7
Received: 16-May-2021, Manuscript No. jcde-21-31513;
Editor assigned: 19-May-2021, Pre QC No. P-31513;
Reviewed: 04-Jun-2021, QC No. Q-31513;
Revised: 20-Jul-2022, Manuscript No. R-31513;
Published:
20-Sep-2022
, DOI: 10.37421/2165-784X.2022.12.463
Citation: Getaneh, Shimelis and Kansal ML. "Pandemic Construction Delay and Cost Overrun Analysis in Water Resource Project." J Civil Environ Eng 12 (2022): 463.
Copyright: © 2022 Getaneh S. This is an open-access article distributed under the terms of the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.
This research aims to identify the most critical factors that influence cost and time overruns in water resource projects and assess the risk associated with cost and time overruns. There were fifty (50) time delay factors and fifty-five (55) cost overrun factors included in this study. Identifying the Cause for the project's delay was greatly aided by studying the literature and discussions with various parties. This questionnaire aimed to assess the severity, frequency of occurrence, and significance of the defined courses. The factor was compared and ranked based on the analyses of the Relative Importance Index (RII). Cost overrun-related factors were categorized into six groups i.e. client, contractor, consultant, labour, external, and equipment whereas, time overrun administration, financial, contractor, consultant, and material-related factors. This factor was compared and ranked based on the analyses of the Relative Importance Index (RII). Based on the studies, contractor and external-related factors significantly impacted the frequency and severity of cost overrun compared to other sub-groups. Similarly, we compared the major contributor factor in the project's running time; based on the analysis of the material-related and financial-related problems; there was a significant impact in increasing the project's frequency and severity, respectively. Furthermore, in this research, the percentage of risk of cost and time overrun was also studied in detail. Based on that, external related factors had a high risk for cost overrun compared to the other five categories, and administration-related factors were also exposed time overruns to be raised.
Cost overrun • Time overrun • Relative Importance Index (RII)
This study covers Delay's risk and cost overrun of water resource construction projects from the Ethiopian perspective. Ethiopia is one of the ancient and non-colonized countries reached in natural resources. Among the natural capacity, water resource is the most and the privileged resource in the country. Ethiopia has over 122 billion meter cube of water resource capacity on both ground and surface [1]. The favourable geographical location and the excellent climate condition made the country get a fair amount of rainfall. However, due to miss management and Lack of water resource structure, people had not been utilized. As research indicates, Ethiopia has 3.7 million hectares of irrigable land; however, 75000 hectares of land were irrigated. The water sector development program main report volume 1(2002), Ethiopia has more than enough hydropower potential of 135 GWh per year. Due to the economic and Delay of project and cost overrun problem, only one percent has been used. From these studies, we will deal with the main Cause of cost and time overrun from Ethiopia's point of view. It implies the impact assessment and analysing the risk of Delay in Water resource projects [2]. The construction industry is one of the activities that are growing the country's growth from time to time it has prevented the Ethiopian economy from being too reliant on the agricultural sector, which accounts for a large portion of its GDP. Construction projects are unique and are an inherent risk due to multi-sector involvement with their interests. The construction industry risks are multiple and can lead to undesirable consequences [3]. construction delay shifts a project schedule beyond the contract date on which the construction involving party agreed to finish. Due to an unwanted increase in estimated cost and highly complex and complicated nature, the project's health would disorder. Delay defines the time consumed over the project contract agreement's specified duration. It can categorize that the time which is taken to complete the project beyond the prescribed contract schedule.so, it can be stated the productive project are the project that is completed per required time for the required purpose at the right place. In this research, delays in Dam construction projects will be considered as the requested additional time to complete the project beyond the original period of contract or, in other words, it is the amount of difference between the planned construction time for the project and the actual time to complete it [4]. They have identified the primary Cause for both times and cost Delay those are owner during construction, in progress payment, ineffective timing and planning by Contractor, Shortage of labour, Shortage of financial by Contractor, government regulation, traffic control and restriction at the site, the Effect of social and cultural factor and accidental factor [5]. factors for cost overrun for drilling groundwater and identified ten primary reasons for the escalation of cost monthly payment difficulty, poor contract management, material procurement, inflation, contract financial difficulty, escalation of material price, cash flow. In the construction industry, during construction, plan and scheduling deficiencies, bad weather, and deficiency in cost estimated., Delay is a big problem that faces projects not to be completed as planned. Client, Contractor, and Consultant are the main actor that delays the project. Various causes of delays in construction projects are classified under these three main parties. Delay can be categorized into five groups: compensable excusable construction project delay, Non-excusable non-compassable Delay, Non-compassable excusable delay construction delay, and concurrent critical and noncritical Delay. An operation's ability can only be, increased if the contract process is improved. Payment adjustments, financial arrangements, inadequate contract management, material shortages, and unreliable approximation of time and cost were among the sixty major factors reported by the routers as contributing to time and cost overruns. Many studies have explored construction delays, their impact on social, economic, and environmental factors that lead the problem to become complicated. They have often depended on Delay's Cause through time overrun, but they have not sufficiently on cost overrun factors. This study's primary goal is to identify the major contributing factors that cause construction projects to be delayed and assess the likelihood of delays and cost overruns in water resource construction projects.
Concept of cost and time overrun
Delay is an activity that creates time needed to complete tasks or activities under a contract to be extended. It is usually expressed as the number of additional days of work required to complete a project in its entirety or part. Described delay as the period spent exceeding the project contract agreement's specified length. It's a way to categorize how long it takes to complete a project after the contract deadline has passed. As a result, it could be claimed that worthwhile projects are done on time and for the right reason right place. Construction delays can be identified as the requested additional time to complete the project after the original contract date or the difference between the planned and actual construction time [6].
Identified as the primary cause for both time and cost overrun were owner during construction, in progress payment, ineffective timing, and planning by contractor, shortage of labour, shortage of financial by contractor, government regulation, traffic control, and restriction at the site, the effect of social and cultural factor and accidental factor. There were ten primary explanations for cost overruns in groundwater drilling, including monthly payment difficulties and lousy contract terms. Management, material procurement, inflation, contract financial difficulty, escalation of material price, cash flow during construction, plan and scheduling deficiencies, lousy weather, and the cost estimate's shortages. The delay was a significant issue in the building industry, with many projects failing to finish on time. The key players in the project's delay were the customer, contractor, and consultant. These three primary players were responsible for a variety of delays in construction projects (Tables 1 and 2).
No. | Factor for cost overrun | ||||
---|---|---|---|---|---|
1 | Delay in delivering the site to the contractor | Cl | 29 |
Delay in reporting the progress of works done | Cs |
2 | Frequent change orders during construction | Cl | 30 |
Low productivity of labor | L |
3 | Late in approving design documents | Cl | 31 |
Shortage of technical staff labor | L |
4 | Unrealistic contract duration | Cl | 32 |
Weak motivation labor | L |
5 | Work suspension by clients | Cl | 33 |
The conflict between labor | L |
6 | Delay in decision making process | Cl | 34 |
Labour nationality | L |
7 | Owner interference | Cl | 35 |
High cost of labour | L |
8 | Delay in change orders by the client | Cl | 36 |
Overtime issues labor | L |
9 | Poor financial control mechanism | Cl | 37 |
Delay in material delivery. | Eq |
10 | Poor coordination and communication b/t contractor | Co | 38 |
Poor material handling on site. | Eq |
11 | Financial difficulties by contractors | Co | 39 |
Inappropriate/misuse of material and equip. |
Eq |
12 | Delay in site mobilization | Co | 40 |
Poor procurement programming of material | Eq |
13 | Often changing sub-contractors | Co | 41 |
Shortage of materials in the market | Eq |
14 | Mistakes during construction by contractors | Co | 42 |
Low quality of materials | Eq |
15 | Poor contractors experience | Co | 43 |
Construction equipment shortage | Eq |
16 | Ineffective planning and scheduling | Co | 44 |
Equipment productivity | Eq |
17 | Ineffective coordination between contractors and other parties | Co | 45 |
Equipment failure | Eq |
18 | Lack of sub-contractor skills | Co | 46 |
Equipment choice. | Eq |
19 | Poor site management by contractors | Cs | 47 |
Corruption | Ex |
20 | Lack of sufficient experience of consultants | Cs | 48 |
Security | Ex |
21 | Delay in reviewing the design documents | Cs | 49 |
Warlords influence | Ex |
22 | Poor inspection plan by consultants | Cs | 50 |
Effect of social and cultural factors external | Ex |
23 | Project design complexity | Cs | 51 |
Permits from related authorities | Ex |
24 | Mistakes and discrepancies in design documents | Cs | 52 |
Land acquisition | Ex |
25 | Poor coordination/communication between consultant and parties | Cs | 53 |
Natural disasters | Ex |
26 | Slowness in giving instruction | Cs | 54 |
Utilities issues | Ex |
27 | Inadequate quality assurance and quality control plans | Cs | 55 |
Foreign labour permits | Ex |
28 | Conflicts amongst consultant with other parties |
No. | Cause of time overrun | Category | Cs | ||
---|---|---|---|---|---|
1 | Effect of hot/cold weather | Co | 26 | Unstable cost and delay in | M |
on the construction and the | preparing special materials | ||||
materials | |||||
2 | Lack of sufficient contact | Co | 27 | Bureaucracy in bidding | Ad |
between consultant and | method | ||||
other groups | |||||
3 | Mistakes and reworks | Co | 28 | Not enough information | Ad |
wanted for them during | before design | ||||
construction | |||||
4 | Domination of construction | Co | 29 | Changes in the laws | Ad |
industry by foreign firms | provided by the | ||||
and aids | government | ||||
5 | Sudden order change by | Co | 30 | Disagreement between | Ad |
owner during construction | consultant and design | ||||
team | |||||
6 | Wrong consideration about | Co | 31 | High number of public | Ad |
the owners requirements | holidays (time) | ||||
7 | Insufficient scheduling of | Co | 32 | Poor contract management | Ad |
project by Contractor | |||||
8 | Delay in decision making | Co | 33 | Poor supervision on the | Ad |
site | |||||
9 | Shortage of equipment | Co | 34 | Traffic facilities | Ad |
10 | Low level of qualification | Co | 35 | Shortage of technical and | Ad |
and technical staff | qualified personnel | ||||
11 | Poor communication and | Co | 36 | Low-speed decision | Ad |
coordination with other | making process | ||||
parties | |||||
12 | Sub-contractor delay work | Co | 37 | Delay in delivering the site | Ad |
to Contractor | |||||
13 | Delay in delivering the | Co | 38 | Not having enough | Ad |
imported materials | experience by consultant | ||||
14 | Effect of subsurface | Co | 39 | Ground problems | Ad |
condition | |||||
15 | Third party final inspection | Co | 40 | Delay in site mobilization | Ad |
and certification delay by a | |||||
third party | |||||
16 | Delay in producing and | Cs | 41 | Late preparation of the | Ad |
completing the design | materials | ||||
documents | |||||
17 | Low level of experience in | Cs | 42 | High cost of maintenance | fi |
design team | of machinery | ||||
18 | Delay in accepting and | Cs | 43 | Inflation | fi |
performing the changes in | |||||
scope of project | |||||
19 | High cost of the qualified | Cs | 44 | Low level of efficiency from | fi |
personnel | the equipment | ||||
20 | Contrast and poor | Cs | 45 | Economical condition of | fi |
communication between | the government | ||||
Contractor and consultant | |||||
21 | Lack of variety of materials | M | 46 | Monthly payment | fi |
in market | difficulties | ||||
22 | Problems in sub- | M | 47 | Inconstancy of the price of | fi |
contractors schedule for | materials | ||||
finishing the project | |||||
23 | Lack of variety of materials | M | 48 | Financial difficulties | fi |
in market | |||||
24 | Rigidity of consultant (not | M | 49 | Mode of financing and | fi |
able to be flexible) | payment for completed | ||||
work | |||||
25 | Unexpected geological | M | 50 | Taxes on the construction | fi |
condition natural disaster | utility and equipment |
There were fifty (50) time delay factors in this research, and fifty-five (55) cost overrun factors are considered. Literature review and discussion with some parties were played grate role in identifying the Cause for the Delay of the project. The questionnaire was created to assess the severity, frequency of occurrence, and significance of the courses listed. There are quantitative and qualitative methods that can be used to understand better how people perceive construction. The quantifiable response will be assessed or analyzed through the quantitative approach, as its name indicates. Qualitative data is another type of data type, as its name indicates it offers more emphasis to the qualitative response. Primary data and secondary data are the two types of information gathered. Primary data is knowledge gathered by researchers in order to manage firsthand information. The questionnaires were sent out by email and hand-delivered to respondents after they had completed them. Structure questionnaires were prepared and distributed to a selected sample to determine the serious causes of Gibbie, GERD, and Rib water supply construction project delays [7]. Several experts, including structural engineers, geologists, hydraulic engineers, electromechanical engineers, and regular laborers, took part in the questionnaire filling. Secondary data was another form of data used in this research. It was a type of data used in a literature review to gather information like cost overruns and delays in the development of a water resource project. It was used to understand better the various theories that relate to the research issue. Literature review content includes books, journals, magazines, the internet, and other research sources. The questionnaires were written with the research objective in mind, focusing on the causes of construction delays and cost overruns in water resources projects. It determines the Cause of the construction project, the effect of delays and overruns on the project, and the importance of those impacts on the project. The questioners majorly consist of
• Respondent background this is the mechanism of gathering the necessary information of the respondent.
• Cause of delay helps collect the data on various Cause of delay happened in the project.
Important index technique
This approach is used to determine the frequency and the severity of the Causes of project execution. Frequent occurrences can often be characterized, often and rarely, whereas severity includes very high, medium, and low (on 4 to 1 point). Assaf and Al-Hejji put formula used to rank cause of delay and cost overrun.
Fico= Σ Xt0 (fco/N)* 100/4
Fito= Σ Xc0 (fco/N)* 100/4
Where xto and xco is the constant expressing weighting given to each response and (ranges from 1 for rarely up to 4 for always), fco and fto is the frequency of response for cost and time overrun, and N total number of responses. In the same manner for a given four points, the hardness or Severity of occurrence can be categorized as very high, high, moderate, and low(on a 4 to 1 point scale).
Fico= Σ Xc0 (fco/N)* 100/4
Sito= Σ Xt0 (fto/N)* 100/4
Where Sico and Sito severity index, x is the constant expressing weighting given to each response and (ranges from 1 for low up to 4 for high), fco and fto is the frequency of response for cost and time overrun, and N total number of responses.
Calculation of these values, the importance index of each course can be known as a function of both severity and frequency index.
Risk assessment
Risk can be viewed in a variety of ways by various academics. Most people, however, consider the risk to be only adverse, but it is characterized as the likelihood of loss or benefit multiplied by the magnitude of the loss or gain. If the chances of occurrence are 100%, we call it certain, and if the probabilities of occurrence are 0%, we call it uncertain. One of the factors that influence the construction industry's performance and execution is the level of risk. Risk management is an integral aspect of the decision-making process in projects.
(R)risk=severityindex(SI)*frequency index(fi)
Rc0= Σ fxc0 (fc0/N)*100/4* Σ SXc0 ( fc0/N)*100/6
Rt0= Σ fxt0 (ft0/N)*100/4* Σ SXt0 ( ft0/N)*100/6
Where Rco and Rto the risk for both cost and time overrun.
Respondent profile
The contractor, consultant, customer, employer, and daily labor, the main contributor in responding to the questionnaires. Twenty-five were questionaries paper distributed to the contractor, and 21 or (84%) responded. Similarly, twenty (20) were allocated to the consultant, and seventeen (17) responded, Fifteen (15) to clients, and 13 responded finally, ten (10) daily labor nine answered. The percentage of validity for contractor, consultant, client, employer, and daily labor is 84, 85,80,80,90, and 78.82, respectively.
Frequency and severity analysis of cost overrun
Contractor related factor (RII=0.66): The Contractor is one of the most prominent factors in the construction project's execution. However, due to internal and external factors, the contractor may fail to meet the project's objectives [8]. The cost overrun dilemma was the critical challenge that put the contractor under difficulty. The concept of cost overrun can be defined in terms of frequency and Severity (Figures 1 and 2). Frequency is the rate at which project cost and time overrun occurs over a certain period or in a specified sample, where the Severity indicates the hardness of overrun on the construction projects. Table 3 describes the rank of the frequency and severity of the cost overrun problem by the contractor. The financial difficulties by the contractor (RII=0.73), poor contractor experience (RII=0.68), a mistake during construction by the contractor (RII=0.656), Lack of sub-contractor skill (RII=0.656),ineffective planning, and scheduling, Delay in site mobilization, often changing subcontractors, poor communication between and other parties, and ineffective coordination between the Contractor and other parties were the main reason for the delay of the Gibe III hydropower project GERD hydropower project and rib irrigation project. On the other hand, the severity of cost overruns due to the contractor could also affect the GERD, Rib, and Gibe III. Those severities of delay include, Lack of subcontractor skill (RII=0.73), poor coordination and communication between contractor and other parties (RII=0.68), financial difficulties by contractors (RII=0.68), and poor contractor experience was the primary factor for cost overrun problem.
No. | Contractor related | f rRII | Rank | sevRII | Rank |
---|---|---|---|---|---|
1 | Poor coordination and | 0.681 | 2 | 0.68 | 2 |
communication b/t | |||||
contractor | |||||
2 | Financial difficulties by | 0.734 | 1 | 0.57 | 5 |
contractors | |||||
3 | Delay in site mobilization | 0.619 | 5 | 0.73 | 1 |
4 | Often changing sub-cont ractors | 0.572 | 6 | 0.63 | 4 |
5 | Mistakes during | 0.656 | 3 | 0.57 | 5 |
construction by contractors | |||||
6 | Poor contractors | 0.681 | 2 | 0.65 | 3 |
experience | |||||
7 | Ineffective planning and | 0.628 | 4 | 0.68 | 2 |
scheduling | |||||
8 | Lack of sub-contractor | 0.656 | 3 | 0.73 | 1 |
skills |
Consultant factor (RII=0.611): Consultants play a crucial role in fostering and carrying out the construction industry's responsibilities. On the other hand, if consultants do not commit from start to finish, it will negatively affect the project's progress. In Table 4, the frequency of poor coordination/communication between consultant and parties (RII=0.7), slowness in giving instruction (RII=0.69), mistakes and discrepancies in design documents (RII=0.63), Lack of consultants' sufficient experience significantly impacted the frequency of delay water resource project(RII=0.61).
No. | Consultant related factor | Fre RII | Rank | Sev RII | Rank |
---|---|---|---|---|---|
1 | Poor site management by | 0.58 | 6 | 0.63 | 5 |
contractor | |||||
2 | Lack of sufficient experience of | 0.61 | 0.56 | 8 | |
Consultant | |||||
3 | Delay in reviewing the design documents | 0.6 | 5 | 0.65 | 4 |
4 | Poor inspection plan by consultants | 0.59 | 6 | ||
5 | Project design complexity | 0.57 | 7 | 0.57 | 7 |
6 | Mistakes and discrepancies in design documents | 0.63 | 3 | 0.65 | 4 |
7 | Poor coordination between consultant and parties | 0.7 | 1 | 0.76 | 1 |
8 | Slowness in giving instruction | 0.69 | 2 | 0.63 | 5 |
9 | Inadequate quality assurance | 0.58 | 6 | 0.57 | 7 |
10 | Conflicts amongst consultant with other parties | 0.58 | 6 | 0.66 | 3 |
11 | Delay in reporting the progress of works done | 0.57 | 7 | 0.68 | 2 |
Poor coordination or communication between consultant and parties (RII=0.76), delay in reporting the progress of work done (RII=0.68), and conflicts amongst consultant with other parties (RII=0.66) were the top three major severed factor.
Equipment factor (RII= 0.674): Equipment or material-related issues were other factors that greatly accelerated the rate of cost overruns. Table 5 shows that poor procurement programming of material (RII=0.73), Shortage of materials in the market(RII=0.73), equipment failure (RII=0.73), equipment productivity (RII=0.71), low quality of materials (RII=0.70),construction equipment shortage (RII=0.68), inappropriate/ misuse of material and equipment (RII=0.63), delay in material delivery, poor material handling on-site and equipment choice is the top ten equipment factor which affects the cost overrun of a water resource project. Equipment can also be described as in terms of material, which means the facilitating of construction material was the big issue in developing countries. Even though material accumulation was sufficient, there was a shortage of transportation and road access such kinds of problems highly worst or severe in the construction project. Based on analyses in the case of our research area, equipment failure (RII=0.44), shortage of materials in the market(RII =0.44), poor procurement programming of material (RII=0.42), poor procurement programming of material, equipment productivity, low quality of materials, construction equipment shortage, inappropriate/misuse of material and equipment, delay in material delivery, poor material handling on-site and equipment choice are the top ten equipment factors that severed cost overrun of a water resource project.
No | Equipment related | RII | Rank | RII | Rank |
---|---|---|---|---|---|
1 | Delay in material delivery | 0.58 | 6 | 0.32 | 6 |
2 | Poor material handling on-site | 0.58 | 6 | 0.41 | 3 |
3 | Inappropriate/misuse of material and equip | 0.63 | 5 | 0.44 | 1 |
4 | Poor procurement programming of material | 0.73 | 1 | 0.34 | 5 |
5 | Shortage of materials in the market | 0.73 | 1 | 0.44 | 1 |
6 | Low quality of materials | 0.70 | 3 | 0.35 | 4 |
7 | Construction equipment shortage | 0.68 | 4 | 0.35 | 4 |
8 | Equipment productivity | 0.42 | 8 | 0.42 | 2 |
9 | Equipment failure | 0.71 | 2 | 0.41 | 3 |
10 | Equipment choice | 0.57 | 7 | 0.35 | 4 |
External related factor: Corruption (RII=0.76), security (RII=0.68), social and cultural (RII=0.68), permit from relative austerity (RII=0.68), utility issue, natural disaster; war load influence, foreign labor permit, and land acquisition the were top ten cost overrun delays factor. Table 6 shows the severity of external related factor occurred due to natural disaster (RII=0.82), corruption (RII=0.81), land acquisition (RII=0.72), the effect of social and cultural factors external (RII=0.706), permit from relative austerity, utility issue, war load influence, and foreign labor permit, have been exposing the construction project not to complete on time per its required budget [9].
No | External related | fre RII | Rank | Sev RII | Rank |
---|---|---|---|---|---|
1 | Corruption | 0.76 | 1 | 0.81 | 2 |
2 | Security | 0.68 | 2 | 0.68 | 6 |
3 | War loads influence | 0.68 | 2 | 0.70 | 5 |
4 | Effect of social and cultural factors external | 0.68 | 2 | 0.706 | 4 |
5 | Permits from related authorities | 0.65 | 4 | 0.68 | 6 |
6 | Land acquisition | 0.5 | 7 | 0.72 | 3 |
7 | Natural disasters | 0.57 | 5 | 0.82 | 1 |
8 | Utilities issues | 0.66 | 3 | 0.66 | 7 |
9 | Foreign labour permits | 0.53 | 6 | 0.53 | 8 |
Labor related factor: Low productivity of labor (RII=0.68), shortage of technical staff labor, weak motivation labor (RII=0.6), the conflict between work (RII=0.57), and high cost of delivery (RII=0.53) was the primary indicator that delay of a water resource project. The severity of the labor- related problem was the most important in developing the selected water resource structure's progress [10]. Weak motivation Labour, High cost of labor, Low Productivity of labor, Low productivity of labor, Shortage of technical staff labor, and weak labor motivation were the most severe problem in exposing the project for unwanted cost overrun (Table 7).
No | Labor-related Cause of Delay | freq RII | Rank | sevRII | Rank |
---|---|---|---|---|---|
1 | Low productivity of laborv | 0.68 | 1 | 0.63 | 2 |
2 | Shortage of technical staff labour | 0.63 | 2 | 0.57 | 5 |
3 | Weak motivation labour | 0.63 | 2 | 0.66 | 1 |
4 | The conflict between labor | 0.6 | 3 | 0.59 | 3 |
5 | Labour nationality | 0.57 | 4 | 0.58 | 4 |
6 | High cost of labour | 0.53 | 5 | 0.66 | 1 |
Client related factor: The client was an essential participant in any construction project. In this case, construction customer is the entity that initiates construction or infrastructure projects at its own cost. The construction client also interprets and translates the needs, desires, and wishes of an organization to set specifications and conditions for construction and construction projects. Clients use a facility to carry out the business or service; thus, the facility is a tool or a technology for serving a function, giving the consumer a secondary interest in buildings. Besides, when it comes to credentials, institutional environments, discretionary powers, the gap between clients and users (Ryd). The client could also affect the project by delaying and running the project. In the case of our selected project, the frequency of problem due to the client include low financial control mechanism (RII=0.82), Delay in change orders by the client (RII=0.72), owner interference (RII=0.68), delay in the decision-making process (RII=0.65) and work suspension by clients (RII=0.62) was the top factor delaying construction. In another way, severity index for a client, the low financial control mechanism (RII=0.73), late in approving design document (RII=0.68), frequent change orders during construction (RII=0.65) was the top three major factor which highly severe the construction project of gibe, GERD hydro project and rib irrigation project (Table 8).
No | Client related factor | Fr RII | Rank | Sev RII | Rank |
---|---|---|---|---|---|
1 | Delay in delivering the site to the contractor | 0.63 | 4 | 0.57 | 4 |
2 | Frequent change orders during construction | 0.53 | 8 | 0.65 | 3 |
3 | Late in approving design documents | 0.57 | 5 | 0.68 | 2 |
4 | Unrealistic contract duration | 0.50 | 6 | 0.56 | 6 |
5 | Work suspension by clients | 0.57 | 5 | 0.53 | 7 |
In general, the average frequency of Contractor (RII=0.66) was the top factor, followed by external (RII=0.634), equipment-related factor (RII=0.633), Client (RII=0.629), Consultant (0.611) and labour (RII=0.607).
Time overrun analysis
Contractor related delay factor: The construction project was delayed due to a contractor-related factor, and it took longer than expected to complete. The frequency of contractor-related time delay factors includes the effect of hot/cold weather on the construction and materials, lack of sufficient contract between consultant and other groups, sudden order change by the owner during construction, the effect of subsurface condition. In another direction, the severity delay factor by a contractor on the respected water resource project was sudden order change by the owner during construction, the effect of hot or cold weather on the structure and materials, and poor scheduling of project by contractor categorized under highly severed factor for the delay of the project (Figures 3 and 4).
Consultant related delay factor: Consultant was the primary factor that affects project completion time. Consultant delay factor can be described in terms of frequency and severity rate or percentage. The frequency of consultant delay factor in time overrun analysis mainly includes high cost of qualified personnel, delay in accepting and performing the project's change in scope, and delay in producing and completing the design document [11]. The severity of consultant delay factor on those selected water resource project included the high cost of the qualified personnel contrast and poor or communication between contractor and consultant or owner, low level of experience in design, and delay in accepting and performing the change in scope of the project were severe the project no to complete on time.
Cause of time delay by material: Lack of variety of material in the market, unstable cost and delay in preparing special material, the rigidity of consultant (not flexible), unexpected geological condition, or a natural disaster, a high-frequency rate lags over prescheduled time. The Severity of unstable cost and delaying preparing unique material, the rigidity of consultant or Lack of flexibility, and Lack of variety of material in the market was the high severity factor delaying the water resource construction beyond the prefixed time.
Cause of time delay by administration: The construction project's administration sector was a major sector in planning, construction, operation, and maintenance. However, this sector may lead the project not to complete on time and increase the completion time over schedule time due to different reasons. That problem may describe in terms of frequency and severity rate of a factor on delaying project. The frequency of poor supervision on-site, traffic facility, Shortage of technical and qualified personal. The severity includes changes in the government's law, ground problem, not having experience by a consultant, not enough information collected, and survey done before design.
Cause of time delay by the financial sector: The financial sector is also another most crucial sector in advancing the development of construction projects. In Ethiopia's financial sector, even the problematic primary industry due to known and unknown reasons. In our selected construction water resource project, high-cost maintenance and machinery, monthly payment difficulty, government's economic condition, and highly frequented financial sector factor delay the project. The Severity of the financing mode and payment for the completed project, monthly payment difficulty, and financial problem were the main reason for the project's lagging. In general, from Table 9, we observe that the average frequency of time overrun that due to the material (RII=0.65), administration (RII=0.642), a contractor (0.64), consultant (0.613), and financial (0.611) were the primary playmaker in delaying those selected project. However, the main factor that exposed the project to a highly severed rate was the financial factor (RII=0.694). The economic factor problem is currently a big issue for developing countries. Since it is related to foreign exchange or currency. Thecontractor (RII=0.664), administration (RII=0.664), material (RII=0.65), and consultant (RII=0.604) also lead the project for delay frequently.
No | The factor for increment severity of time delay | Avf RII | Rank | AVs.RII | Rank |
---|---|---|---|---|---|
1 | Cause of time delay by material | 0.650 | 1 | 0.650 | 3 |
2 | Cause of time delay by administration | 0.642 | 2 | 0.664 | 2 |
3 | Cause of time delay by contractor | 0.640 | 3 | 0.664 | 2 |
4 | Cause of time delay by consultant | 0.613 | 4 | 0.604 | 4 |
5 | Cause of time delay by financial |
0.611 | 5 | 0.694 | 1 |
Risk of cost overrun
External related factor (Risk=43.578%): Based on analysis, the problem mainly result from corruption (Risk=61.7%), permit from related Auterity (Risk=49%) and security (Risk=46.2%). Whereas, labor-related factor (Risk=40.613%), was mainly due to labor nationality (Risk=51%), the weak motivation of labor (Risk=44.9%), and low productivity of labor (Risk=44.6%) (Figure 5).
Contractor-related factor (Risk=40.6127%): The Contractor was one participant in progressing the selected water resource project's construction. The contractor-related problem may result in the project too late and fail. The contractor-related problem had a considerable risk on the construction project. In the case, our selected project, the risk of cost overrun delay is Lack of subcontractor skill (RII=48.2%), ineffective planning and scheduling (RII=45.4%), poor contractor experience (RII=44.7%) are the top three major factor which highly risks on the completion of the project.
Client related factor (Risk=37.87%): The client-related group risk factor was the most critical factor that causes the cost overrun to be raised. The main risk of cost overrun by the client was poor financial mechanism (RII=59.9%), Delay in a change of order by the client (RII=40.9%), late in approving design document (RII=40.9%) were the major risk on the completion of our selected project.
Consultant related factor (Risk=37.875%): The consultant was one of the stakeholders in facilitating the construction of the water resource project. On the other hand, the consultant's problem also leads the project not to complete on time. It makes the project to be under pressure .the risk of a consultant was the product of the frequency of cost overrun delay by Consultant and the Severity of cost overrun Delay by Contractor. Based on that, the risk of consultant on our selected water resource construction project is poor coordination or communication between consultant and parties (RII=50.1%), slowness in giving (RII=43.4%), mistake and discrepancies in design document (RII=41.4%).
Equipment related factor (Risk=25.64): Shortage of material in the market (Risk=32.6), equipment productivity (Risk =29.2%) and construction equipment shortage (Risk=29%).were mainly the major risk factor that would result for the increment of risk of the water resource project (Table 10).
No. | Risk factor | RII | Rank |
---|---|---|---|
1 | External related factor | 0.44 | 1 |
2 | labour related factor | 0.41 | 2 |
3 | Contractor related factor | 0.40 | 3 |
4 | Client related factor | 0.37 | 4 |
5 | Consultant related factor | 0.37 | 4 |
6 | Equipment related factor | 0.25 | 5 |
Risk of time overrun on the construction of water resource project
The risk of time overrun in our selected research area was categorized under broad five groups: administration, financial, Contractor, and material were the influential groups that show risk (Figure 6). Administration gaps play a big hand in resulting a negative role in delaying those selected projects not to complete on time, and its trouble (Risk=0.426) became very high while comparing to others. The second significant contributor in enhancing and developing the risk of our research area was the financial problem (Risk=0.424). Financial problem was one of the major concerns since Ethiopia is a developing country, and there were shortage exchange and another related issue. The third case which leads the project to risk was Contractor (Risk=0.424) related problem. The material-related problem (Risk=0.42) was the fourth in its risk. (Risk =0.37) The last but not least factor in exposing the construction project to not complete per its preschedule was a consultant-related problem (Table 11).
No. | The factor for increment risk of time delay | AV.RII | Rank |
---|---|---|---|
1 | Cause of time delay by material | 0.42 | 3 |
2 | Cause of time delay by administration | 0.426 | 1 |
3 | Cause of time delay by contractor | 0.424 | 2 |
4 | Cause of time delay by consultant | 0.37 | 4 |
5 | Cause of time delay by financial | 0.424 | 2 |
Managing time and cost overrun in construction projects has been considered an essential process to achieve projects objective within the prescribed time for required purposes. This research's main objective is to determine the major contributing factor that delays the construction project and analyses the risk of delay and cost overrun of water resource construction project. To analyze studies, we obtained information through a questionary survey conducted in Ethiopia. Basically, the Cause of cost and time overrun was obtained from literature review and 105 key factors for both time and cost overrun. According to our analyses, the major reason for the rising frequency of cost overrun was the contractor-related factor. An external factor was the severity factor for cost overrun of the construction of Grand Ethiopian renacance dam, Gibe III, and Rib irrigation project. The second objective of this research is determining time overrun of the selected water resource project. Based on that, the frequency of time overrun or delay was occurred by material related factor and the severity of the time overrun is maximum due to financial related problem. This selected research's final objective was determining the factor that exposes for the increment of risk for both cost and time overrun. Accordingly, the external related factor for cost overrun and administration related factor was for time overrun.
Google Scholar, Crossref, Indexed at
Google Scholar, Crossref, Indexed at
Google Scholar, Crossref, Indexed at
Google Scholar, Crossref, Indexed at
Google Scholar, Crossref, Indexed at
Google Scholar, Crossref, Indexed at
Journal of Civil and Environmental Engineering received 1798 citations as per Google Scholar report